Moving nodes to new data center
shulemmosko
33 Posts
February 23, 2022, 8:58 pmQuote from shulemmosko on February 23, 2022, 8:58 pmHi what is the process of moving my petasan/ceph cluster to a different data center can I just shut all nodes down and power back up in the new data center? or are there things to consider before moving the cluster?
Thanks!!
Hi what is the process of moving my petasan/ceph cluster to a different data center can I just shut all nodes down and power back up in the new data center? or are there things to consider before moving the cluster?
Thanks!!
admin
2,930 Posts
February 23, 2022, 10:06 pmQuote from admin on February 23, 2022, 10:06 pmYes you can shut down the cluster no problem. It would be better to not have any client writes during the shutdown, also maybe better to shut down the nodes all at once rather than several minutes apart, again not a must but better.
Yes you can shut down the cluster no problem. It would be better to not have any client writes during the shutdown, also maybe better to shut down the nodes all at once rather than several minutes apart, again not a must but better.
shulemmosko
33 Posts
February 23, 2022, 11:55 pmQuote from shulemmosko on February 23, 2022, 11:55 pmThanks! so there is no need to put the cluster into maintenance mode? like, turn off fencing, etc?
Thanks! so there is no need to put the cluster into maintenance mode? like, turn off fencing, etc?
admin
2,930 Posts
February 24, 2022, 1:13 amQuote from admin on February 24, 2022, 1:13 amno need you as are shutting down the entire cluster.
no need you as are shutting down the entire cluster.
shulemmosko
33 Posts
March 1, 2022, 2:48 amQuote from shulemmosko on March 1, 2022, 2:48 amThank you! the move went smoothly with no problems.
Thank you! the move went smoothly with no problems.
Moving nodes to new data center
shulemmosko
33 Posts
Quote from shulemmosko on February 23, 2022, 8:58 pmHi what is the process of moving my petasan/ceph cluster to a different data center can I just shut all nodes down and power back up in the new data center? or are there things to consider before moving the cluster?
Thanks!!
Hi what is the process of moving my petasan/ceph cluster to a different data center can I just shut all nodes down and power back up in the new data center? or are there things to consider before moving the cluster?
Thanks!!
admin
2,930 Posts
Quote from admin on February 23, 2022, 10:06 pmYes you can shut down the cluster no problem. It would be better to not have any client writes during the shutdown, also maybe better to shut down the nodes all at once rather than several minutes apart, again not a must but better.
Yes you can shut down the cluster no problem. It would be better to not have any client writes during the shutdown, also maybe better to shut down the nodes all at once rather than several minutes apart, again not a must but better.
shulemmosko
33 Posts
Quote from shulemmosko on February 23, 2022, 11:55 pmThanks! so there is no need to put the cluster into maintenance mode? like, turn off fencing, etc?
Thanks! so there is no need to put the cluster into maintenance mode? like, turn off fencing, etc?
admin
2,930 Posts
Quote from admin on February 24, 2022, 1:13 amno need you as are shutting down the entire cluster.
no need you as are shutting down the entire cluster.
shulemmosko
33 Posts
Quote from shulemmosko on March 1, 2022, 2:48 amThank you! the move went smoothly with no problems.
Thank you! the move went smoothly with no problems.